Deflection Test at Kharagpure (South Eastern Railway)

 
Carried out Deflection Test according to Clause 10.5 of IRS Dridge Code for PSC Slab of Spain 32.75 Mts and 13.4Mts of Test Load of 644 MT and 285 MT respectively for Proposed 3Rd Railway Line between Panskura and Kharagpur in South Eastern Railway for Rail Vikas Nigam Ltd.

Bored Cast-in-Situ Vertical reinforced concrete Pile by Rotary method at penna barrage (Nellore)

 
Installing Bored Cast-in-Situ Vertical reinforced concrete Pile by Rotary method of 1000 & 1200 MM Dia as well as Testing Work for Penna Barrage cum Bridge of Nellore,A.P. (Package#6) of Coastal Projects Limited. A Project of Irrigation Department, ( Government of Andhra Pradesh).

Pile Foundation By Hydrualic Machine

 
Providing Pile foundation and Testing work of 900mm dia by Rotary method ( By Hydraulic Machine) for Jaithari Thermal Power Plant Jaithari, Anuppur, MP.

Pile Load Test For DMRC

 
Carried out Pile Load Test on 1000mm dia Pile for Design & Construction of Viaduct & Two Elevated Station, Rohini Sect-18 & Badli to Jahangirpuri –Badli Corridore of Delhi MRTS Phase-III Project.A(DMRC) Delhi Metro Rail Corporation Ltd Project

Pile Load Test For Northern Railway

 
Carried out Pile Load Test on 1000mm dia Pile for Design & Construction of Viaduct & Two Elevated Station, Rohini Sect-18 & Badli to Jahangirpuri –Badli Corridore of Delhi MRTS Phase-III Project.A(DMRC) Delhi Metro Rail Corporation Ltd Project

Deflection Test For Airport Express Metro (DMRC)

 
Carried out Pile Load Test on 1000mm dia Pile for Design & Construction of Viaduct & Two Elevated Station, Rohini Sect-18 & Badli to Jahangirpuri –Badli Corridore of Delhi MRTS Phase-III Project.A(DMRC) Delhi Metro Rail Corporation Ltd Project